We build private houses and guest properties in Makhinjauri: design, permit, foundation, structure, engineering and finishing. Seven kilometres from our base in Batumi.
The order of works is fixed by the slope
Almost every plot here is on a gradient, and that sets the sequence. The retaining wall and drainage come first, the excavation and foundation after. Two reasons: once the house is up, machinery can no longer reach the slope and everything is done by hand at several times the cost; and the ground load has to be taken off before digging, otherwise the pit edge collapses into the excavation. Reversing the order is the most expensive mistake available on this terrain, and it is the one we are most often called in to fix.
The railway and the road below
For a plot close to them we plan the layout so bedrooms face away and the living space opens to the sea rather than to the tracks. We say at the sketch stage what the noise situation actually is, because it is easier to design around than to insulate afterwards.
What we check before you buy
Zone and building coefficient, slope and geology, where surface water enters and leaves the plot, access for a concrete mixer, and the distance to utilities. Sometimes the house you have in mind needs retaining work that costs more than the shell, and it is far better to know that before the deposit.
Timing, price and warranty
Design and permit one to three months, then seven to nine months of works. Payments against completed stages, weekly photo report, five-year warranty on the structure.