We build private houses and guest properties in Makhinjauri: design, permit, foundation, structure, engineering and finishing. Seven kilometres from our base in Batumi.

The order of works is fixed by the slope

Almost every plot here is on a gradient, and that sets the sequence. The retaining wall and drainage come first, the excavation and foundation after. Two reasons: once the house is up, machinery can no longer reach the slope and everything is done by hand at several times the cost; and the ground load has to be taken off before digging, otherwise the pit edge collapses into the excavation. Reversing the order is the most expensive mistake available on this terrain, and it is the one we are most often called in to fix.

The railway and the road below

For a plot close to them we plan the layout so bedrooms face away and the living space opens to the sea rather than to the tracks. We say at the sketch stage what the noise situation actually is, because it is easier to design around than to insulate afterwards.

What we check before you buy

Zone and building coefficient, slope and geology, where surface water enters and leaves the plot, access for a concrete mixer, and the distance to utilities. Sometimes the house you have in mind needs retaining work that costs more than the shell, and it is far better to know that before the deposit.

Timing, price and warranty

Design and permit one to three months, then seven to nine months of works. Payments against completed stages, weekly photo report, five-year warranty on the structure.

All services: Makhinjauri.

How we work

  1. 1Plot and documents
  2. 2Design and estimate
  3. 3Foundation and shell
  4. 4Engineering and finishing
  5. 5Handover

Services: Construction in Makhinjauri

House construction

Private houses in block with a monolithic frame: geology, foundation, structure, engineering and finishing. Five-year warranty on the…

Extensions and added floors

Extending an existing house with a structural survey and full documentation, including the change of area in the…

Commercial construction

Guest houses, small hotels and apart-buildings: layout planned from the economics, not from the square metres.

Facades and roofing

Roofs, gutters and facade systems built for two thousand millimetres of rain, salt air and horizontal storms.

Timber frame houses

A house closed within one warm season: lighter structure, simpler foundation, easier delivery to difficult plots. Kiln-dried timber…

Retaining walls and slopes

Terracing, retaining structures and drainage. On a slope this is structural work, and it comes before the excavation.

Fences and landscaping

Fences, driveways, paths, drainage and outdoor lighting — the part of a plot that decides how it looks…

Reconstruction

Rebuilding old houses and changing a building's use: survey first, then two estimates — rebuild or demolish and…

Landscaping works

Terraced gardens, lawns, planting, irrigation and path lighting for a subtropical plot that grows fast all year.

The same service in other cities

All about the service: Construction

Our properties: Makhinjauri

Frequent questions

Why build the retaining wall before the house?

Because afterwards machinery cannot reach the slope, and the ground load must be removed before excavation. The reverse order costs several times more.

Can you check a plot before I buy it?

Yes: zone and coefficient, slope, ground and water, access for machinery, distance to utilities.

Does the railway affect the layout?

It does. We orient bedrooms away from it and say honestly what the noise is like before the design is fixed.

What if the plot needs a large retaining wall?

We price it separately and say plainly when it costs more than the house shell. That decision belongs before the purchase.

How long does a house take here?

Seven to nine months of works after the permit, with the slope works at the start rather than the end.