We renovate apartments, chalets and guest properties in Bakuriani: finishing from a frame in new developments, full renovation, preparation for the winter season.
The deadline is December, not spring
The season is winter, and the New Year dates — the most expensive of the year — are booked in autumn. So the schedule runs backwards from December and includes the furniture, the outfitting and the photographs, not just the finishing. If the dates do not work we say so before signing rather than halfway through, because a property that opens in February has missed the part of the season that pays for the rest.
What actually decides the ratings
Not the finish but the practicalities. A ventilated drying zone for clothes and boots, a boot tray by the door, hooks with spare capacity, storage for skis and boards that does not block the hallway, underfloor heating in the bathroom, blackout curtains and reliable internet. We build these into the layout rather than adding them afterwards, because in a studio there is usually nowhere left to put them once the walls are finished.
Technical priorities
Insulation of the envelope, snow load on the roof and where the snow sheds, and protection of pipework from freezing during power cuts. A property that cannot be heated through in January gets winter reviews that follow it into the next season.
Timing and price
Frame finishing six to fourteen weeks, cosmetic work two to four. A property needed for December starts in summer or early autumn. Contract remotely, weekly photo report, payments against completed stages.